Production planning

How to spot material shortages before production starts

Before releasing a work order, check whether the stock available to that order covers every component in its bill of materials (BOM). One missing component can hold up the whole build.

A worked example for 20 assemblies

This example uses sample data from the Hamvara Order to Delivery demo. It assumes no existing reservations, scrap or inbound stock.

ComponentPer assemblyRequiredAvailableShortage
Cable2 m40 m60 m0 m
Connector2403010
Terminal4801200

The connectors cover 15 assemblies. To release all 20, confirm that the remaining 10 connectors will be available by the date production needs them.

Calculate the shortage for one component

Required 40 · Shortage 10

Use the same unit for usage and stock. Enter usable stock after subtracting reservations for other orders.

What to check before releasing the order

  1. Use the current BOM revision and multiply each component quantity by the order quantity.
  2. Subtract stock already reserved elsewhere and exclude stock awaiting quality approval.
  3. Check whether incoming material will be usable by the production need date. If a shortage remains, confirm a purchase, reschedule, or release a smaller batch when feasible.

When orders share a component, allocate the available stock in priority order. Update the balance after every allocation so the same stock is not promised twice.

Try the workflow in Hamvara MRP